Canwick Avenue roadworks

Starting on 17th February until mid June 2025, extensive works will begin on Canwick Avenue to install a roundabout at the junction with Lichfield Road.

During this time, the contractor will work up t0 6 days per week

Phase 1: 17/02/2025 – 24/03/2025: Offline works – works to the land opposite side of the Lincoln Road, no carriageway incursion.

Phase 2-4: 24/03/2025 – 09/06/2025: Multi signal traffic management will be in place to the Lincoln Road & Lichfield Road carriageway

Phase 5: 09/06/2025 – 13/06/2025: Road Closure – final surfacing to the Lincoln Road & Lichfield Road carriageway.

 

If you have any queries or complaints either now or as the works progress, these should be directed to MV Kelly enquiries on 0121 708 500 / enquiries@mvkelly.co.uk.

Published: Monday, 17th February 2025