Indicative Project Timetable
| Reference | Action | Status |
| VH01 |
Obtain quotation from Parkinson’s Partnership for specialist tax advice |
Completed |
| VH02 |
Receive written quotations from the three companies |
Completed |
| VH03 |
Finalise “Design Build vs Design Bid Build Procurement” Meeting Paper |
Completed |
| VH04 |
Finalise “Consultation Framework” Meeting Paper |
Completed |
| VH05 |
Develop draft “Outline Project Plan” |
In progress |
| VH06 |
Finalise “Quotations Report” Meeting Paper |
Completed |
| VH07 |
Consider quotation from Parkinson’s Partnership for specialist tax advice |
Approved |
| VH08 |
Approve proposed consultation framework |
Approved |
| VH09 |
Receive RFO recommendation to procure a contractor to design and oversee the full project. |
Approved |
| VH10 |
Consider quotations to appoint a contractor for the agreed procurement method. |
Approved |
| VH11 |
Approve design, outline costs, consultation materials in line with the framework (VH09) |
Approved |
| VH12 |
Begin work on VAT implications with Parkinson’s Partnership |
|
| VH13 |
Carry out consultation in accordance with the framework agreed (VH09) |
|
| VH14 |
Consider consultation feedback report to determine whether to proceed |
|
| VH15 |
Approve application to DLHC for a Public Works Loan |
|
| VH16 |
Complete application to a relevant body for a loan |
|
| VH17 |
Consultant to complete planning application documentation. Council to approve submission to NKDC. |
|
| VH18 |
Approve draft 23/24 budget with provision to meet cost of borrowing |
|
| VH19 |
Develop programme and schedule of work with consultant for permissions and consents, tendering for a construction contractor, prestart requirements through to construction phases. |
|
| VH20 |
Approve project specification prior to building regulations (include room specifications & data sheets). |
|
| VH21 |
Carry out tender process and confirm successful contractor |
|
| VH22 |
Construction phase commences with regular updates to council from contractors. |